A Pre-Inspection Briefing (PIB) is the first official activity at a facility during an industry inspection. It serves to provide OPCW inspectors with enough information to design an inspection plan in the least intrusive manner possible.

PIB

What happens during a PIB 

Facility representatives provide a PIB presentation to OPCW inspectors. The PIB should take no longer than 3 hours. It may be presented in various forms, such as a PowerPoint presentation, a projection, hardcopies, etc. 

Before the PIB, it is recommended to provide hand-outs of the presentation material to OPCW inspectors. Any facility and/or process diagrams may be handed out as a separate hardcopy document to allow for better control over such documents during inspection activities. 

OPCW inspectors will return all the PIB materials at the end of the inspection.

How to prepare a PIB 

OPCW provides PIB guidelines to assist facilities in preparing a thorough, relevant, and accurate technical briefing about the facility. The guidelines are intended for use by industrial facilities subject to Article VI inspections under the Chemical Weapons Convention (CWC) and are recommended as reference only. 

There are different PIB guidelines for Schedule 2, Schedule 3, and OCPF facilities.  

PIB guidelines 

SECIAC

The interministerial committee for the implementation of the Chemical Weapons Convention, established by presidential decree no. 06-178 of 31 May 2006.

Contact

Email:seciac@mdn.dzPhone:+213 21 90 53 42

Fax:+213 21 90 53 22

PO Box 184, Les Tagarins, Ministry of National Defence, 16000 Algiers, Algeria

Operator area